Airport Link Now Fully Up and Running

In June I wrote about my first ride on the Bangkok Airport Rail Link (ARL), which spent the past few months running a limited test service.  The line has both a local and express service, the express promising to move you from the airport to the center of the city in fifteen minutes.  The trial run for the past few months, though, only featured the local service.  Two weeks ago the express portion was brought on line and the system was officially opened, so I went for another ride to check it out.

Now that all the stations were in operation, I decided to ride the express from the Makkasan terminal station (located near Asoke between Rama IX Expressway and Petchaburi Roads) nonstop to the airport, and then ride the local service back to Phaya Thai station, where the ARL connects with the BTS Skytrain.

P1030547

Back in June one problem I noticed was that the ARL station (on the right in the picture) didn’t physically connect with the BTS station (on the far left).  In fact, there was a gap of a good 5 meters, meaning that you had to walk down the stairs from one station, along the road, across the train tracks, and then ascend an escalator into the other station.  Not convenient at all – especially for someone with suitcases!

P1060240

I’m glad to report that on opening day, they had a connector bridge just barely finished (work was still underway but a narrow walkway was opened through it) that takes you from the paid area of the BTS station (in the background) to the public area of the ARL station (in the foreground).  The operator of the BTS has added fare gates and a ticket window so you can enter and exit the station conveniently, walking directly to the ARL station.

Amazing, but true – there was some amount of advance planning and coordination between the agencies!

P1060215

Unfortunately, I can’t say the same for the Makkasan Station, a beautiful, modern facility that is meant to offer the convenience of checking in for your flight at the station, checking your bags, and then being able to whisk off to the airport without the worry of lugging your suitcases with you.

P1060222

The station is set back some 200 meters (650 feet) from Asoke Road, a heavily congested north-south artery, and some 500 meters from the Petchaburi MRTA subway station exit.  Despite more than three years of construction, there is no direct pedestrian access between the MRTA and ARL and no vehicular ramps connecting the station to the southbound (inbound to the city) side of Asoke.

Illustration as to why this is a problem:

As I was walking from the subway station to the ARL station, a very pedestrian unfriendly route, I came across a family of travelers, pulling their suitcases from the ARL station.  I asked where they were heading, ready to give directions, and they were looking for a taxi.  Of course, the driveways weren’t open and no taxi queue was up and running, so they had to walk the 200 meters to the street and try to flag a taxi down.  To top it off, the taxi would be going the opposite direction from where they were headed.

P1060221
Open building but no taxis or any other traffic allowed up to the facility.

A week after the ARL opened, the State Railways of Thailand, which owns and operates the system, announced they would build an elevated pedestrian walkway to the subway station and would build ramps so cars could access the station from all directions.  Give them two years and then things might work better.

P1060220

The State Railways owns a huge tract of land around the Makkasan station, what used to be their main switch yards and maintenance facility.  Their grand vision is to eventually develop all of this – enough room for 20 or more skyscrapers – into a large mixed-use facility of offices, hotels, convention center, shopping, and maybe some residential.  At that point in time, it would be conveniently located.  Until then, it is not really near much of the city.

In fact, that is probably the reason they chose to make Makkasan station the in-city terminal.  They stand to make a lot of money (and maybe, for the first time in 50+ years, turn a profit?) from land development.  The obvious place for the in-city terminal would have been Phaya Thai station, adjacent to the BTS Skytrain.  Better synergy with the transit systems.

P1060224

The express train to the airport is quite nice.  The station is air conditioned and well signed, if lacking in taxis.  The trains run every fifteen minutes and the cars are comfortable with forward and rear facing seats, luggage racks, and overhead storage for small items.  The train is also very fast – top speeds supposedly of 150 kmh, but I think it is more like 120 most of the way.

P1060231

A view of the roads leading from the highway to the airport as we zoom past, arriving exactly fifteen minutes after leaving Makkasan.

My assessment: The system is a very welcome addition to the transit network here in Bangkok.  The local line, which connects from the airport directly to the Skytrain with six intermediate stops, is very useful and will probably do a lot of business, what with the rapidly-expanding suburbs to the east of the city.  The airport express itself isn’t useful as you pay more and wind up at a station that isn’t convenient to anything.  My advice – if you are arriving in the city and want to use the train, use the local line.  Or, if there are more than two of you, take a taxi.  In another two or three years, once the connections to the Makkasan station have been built and it is more convenient, I might revise my opinion.

 

First Ride on the Bangkok Airport Link

Three years late, the rail line to the Bangkok Suvarnabhumi International Airport has finally started running, although on a limited, trial basis.  Last week I headed out for a look at this latest addition to Krungthep’s transit infrastructure.

The new airport, Suvarnabhumi, opened more than three years ago about 30 km east of the heart of the city.  The planned rail service, the so called “pink line,” suffered through interminable delays caused for any number of reasons, not the least of which might have to do with the State Railways of Thailand’s notorious inefficiency.  The SRT, which owns the right-of-way, built, and will eventually operate the pink line, has never turned a profit in its more than half-century of operations.

Nonetheless, I’m excited that another piece in the transit puzzle is nearly put into place as the line started limited trial service almost two weeks ago.

Airport Link Map

The pink line is actually two lines: the darker line is the city line, which will make multiple stops between the airport and Phaya Thai, which is currently the westernmost station.  As you can see in the above map, there were several planned but unbuilt stations, shown with station names in outlined font.  The second, light pink line is the airport link, which will run nonstop between the airport and the Makkasan station (at Asoke and Petchaburi Roads), where the in-city terminal will be located.

If all goes according to plan, passengers will be able to check in for their flights at Makkasan station, receive boarding passes and drop off their bags, then ride on the train to the airport.  Their bags will be carried in a secure storage area and, already ticketed, will go from the train directly into the airport’s baggage system.  It sounds like there will be some delay before that part is operational.

Additionally, the plan is that passengers on the pink line will be able to connect with the BTS Skytrain at Phaya Thai and with the MRT subway at Makkasan-Petchaburi.  Sadly, it appears that neither connection is currently built.

P1030547

I met up with Bill and Ken, two friends with an interest in things both transit and aviation related, at the Phaya Thai BTS station to give the pink line a try.  During this trial run, only the two end stations – Phaya Thai and Airport – are operational on the pink line.  The train service is running weekdays from 7-10 am and 4-10 pm nonstop between these stations, although some intermediate stops will be introduced next week.  This trial run is free and will last until August, when the full system is supposed to be in service.

Above, you can see the Phaya Thai station of the pink line, the big concrete behemoth on the right, and a ramp that is supposed to connect to the Phaya Thai BTS station on the left.  You’ll notice, though, that the ramp stops about 5 meters short of the BTS station.  I’m curious about this because passengers will have to walk down to the street level, along 100-200 meters of broken, dirty sidewalk, cross an active railway line, and then ascend into the second station, regardless of which way they are connecting.

P1030550

Above: Flagman at the active railroad tracks that passengers connecting between the pink line and BTS have to cross, directs cars off the track as a train approaches.

My theory for this is that the two systems didn’t communicate very well, even though the BTS has been running for more than ten years so certainly wasn’t an unknown entity.  The ramp would connect a paid area in the BTS station with a public area in the pink line station.  So someone is going to have to pay to build and maintain turnstiles and a BTS ticket booth somewhere at the connection point.  This is insane because the three rail systems in town are supposed to be moving to a common ticket platform – one ticket, all systems – so the ramp should lead from the paid area to another paid area, not pass through a public area of the pink line station.

Anyhow, we walked across the railroad tracks with no problems and took the elevators up several levels in the new pink line station, being directed by friendly guards the whole way.

P1030558

The trains (these are the city line trains being used for the test run, not the airport link trains) are from Siemens and they look nice enough.  The stations along the line are not very impressive, a collage of grey concrete and grey metal.  Only the Makkasan and Airport stations are air conditioned.

P1030423

The line was pretty well used when I took it about 4pm.  By the time the train left, the seats were full with many of the passengers looking like airport employees or people who live out in the eastern suburbs.  There were also many local tourists traveling just to see the new train and, surprisingly, a few people actually using the train to get to the airport with their bags. 

Once the line is fully operational, the city line will charge between about 10-40 baht (up to US$1.25) and the airport link will charge 150 baht (US$4.75).  I would assume that the seating arrangement on the airport link train will feature pairs of seats facing forwards and backwards along with storage space for carry-on baggage.

P1030427

Notice the wide gap between the train and the platform.  It looks like there is a ledge under the door that can be extended, but they were not doing that.

P1030421

The monitors in the station show a video of the route, alternating between Thai and English.  There is also a countdown clock until the next departure – shown in seconds!  I’ve never seen a train station that shows countdown time in seconds.  And, believe me, SRT isn’t the sort of prompt organization that runs things to the second.

P1030422

Looking east from Phaya Thai station towards the Ratchaprarop station, the two closest stations on the line.

P1030570

The ride itself was very smooth, with the exception of one station midway through the line where there is a passing lane.  We had to slow down significantly to change tracks, breaking our otherwise good speed of approximately 120 kmh or 75 mph.  We were going faster than all but the fastest taxis on the expressway that parallels the tracks most of the way to the airport.

Along the way, there was a nice view of the many new housing development springing up near the airport and the new stations on the pink line.  This line will probably become very useful, less for airport passengers and employees, but more for locals who live to the east of the city and need a fast way to commute into town to their offices.

P1030586

It took just about 20 minutes to go from Phaya Thai station to the airport.  I understand that the airport link service from Makkasan to the airport will be about 16.  The train pulls into the sub-basement of the car park structure, connecting directly into the terminal building.  A quick ride up the elevator or moving sidewalks and you are at the arrivals and departures levels.  Very convenient on this end of the line.  In the future, you will be able to walk through this station to the airport hotel, which you currently have to take a shuttle van to.  The station will also have various retail shops, although those are all located on the hotel side of the station, which doesn’t make much sense.

There are some potential cons to the system right now and I’ll have to wait and see how it works once the whole system is up and running, then I’ll talk more about the cons if they haven’t been addressed.  For the moment, I’ll simply say that I’m glad additional transit options are opening and I hope that we’ll see several more in the next few years.

P1030413

Speaking of which, one has to wonder where the pink line, which ends just to the west of the Phaya Thai station, will go in the future.  The master plan shows this line continuing, turning north and heading towards the old Don Meuang airport (and beyond) and also turning south and heading to the current Hualamphong train station and then underground, across the river, and southwest to Samut Sakhon province.  Ambitious!